RETAIL STORE AT MIAMI DESIGN DISTRICT
Italian Architect: Ezio Riva, Riva Studio, Milan
US Architect: Alfred Ravelo, Behar Font & Partners, Miami, FL
General Contractor: Mauro Burgio, ForSite Builders, Coral Gables, FL
US Architect: Alfred Ravelo, Behar Font & Partners, Miami, FL
General Contractor: Mauro Burgio, ForSite Builders, Coral Gables, FL
project status 01-31-015
current schedule
|
project status 12-06-14 AND 12-18-2014
- Rough Inspections Passed: Electrical, Mechanical, Plumbing, Fire Alarm
- Rough Inspections Pending: Fire Sprinkler and Security/Access Control
project status 12-06-14 AND 12-08-2014
- An important AC rough inspection was passed on 12/10. Ok to close ceiling for mechanical.
- Electrical rough inspection is scheduled for 12/12. After this inspection we will submit documents to request temporary power.
- We were able to obtain power by running an extension to the basement, which will help us reduce nighttime work. Previously we could only have power at night, because the Design District did not allow us to run an extension cord outside of the unit.
- We are currently experiencing a delay in plumbing installation that could prevent installation of drywall. The Design District did not provide a sanitary sewer connection point under PC137. We are working with our engineer to develop a solution as fast as possible. See plumbing drawing below for details.
project status 12-01-2014
- 12/01: Coordination meeting with Tyco Security and NP Electric - determined location of all CCTV camera boxes and power outlets required for security & access control.
- Design District is enforcing work restrictions this week. Work had to stop at 1:00PM on 12/01. We will try to obtain permission to work within the suite with door closed.
project status 11-25-2014
project status 11-21-2014
project status 11-11-2014
- Construction Started on October 30, 2014
project status 10-24-2014
- Certain items for Vanilla Shell still remain to be completed
- Will request hard completion date from the Design District
project status 10-15-2014
- Vanilla Shell contractor scheduled to deliver space on 10/23/2014
- Master Permit was issued on 10/16/2014
- Pre-Construction meeting scheduled for Monday, 10/20/2014